November 8th Report Posted 8 Nov 2007 IN: General BY QCL
![]() Totem House Construction is Well Underway! We're pleased to say that the construction phase of Totem House is well under way. October was the time for the "dirty work" with prep and foundation construction. The log components arrived by barge on October 23rd, just in time to move onto the next phase. Concrete is all mixed on site with pre-packaged dry mix, a little water, a cement truck and a good bit of innovative thinking! Kudos to our construction crew onsite who are doing a great job amidst the challenges posed by the Charlotte's fall weather! As you can see in the photos, they're ready to start the erection of the log walls so the progress should be particularly exciting over the next few days! Click here to see a photo gallery of Totem House under construction. Stay tuned for up-to-date reports right here! |